Capacity Curtailment on the ES-FR border for delivery period 13-12-2024
1. TSO(s)*:
RTE-TSO
2. Identification of affected Long Term Transmission Rights:
ES-FR
3. Triggering event:
Curtailment to ensure operation remains within Operational Security Limits
4. Affected volume in MW / hour for each concerned period:
13-12-2024 08:00 - 09:00 690 MW
13-12-2024 17:00 - 18:00 690 MW
13-12-2024 18:00 - 19:00 690 MW
13-12-2024 19:00 - 20:00 690 MW
13-12-2024 20:00 - 21:00 690 MW
13-12-2024 21:00 - 22:00 690 MW
5. Amount of LTTR remaining after curtailment:
13-12-2024 08:00 - 09:00 0 MW
13-12-2024 17:00 - 18:00 0 MW
13-12-2024 18:00 - 19:00 0 MW
13-12-2024 19:00 - 20:00 0 MW
13-12-2024 20:00 - 21:00 0 MW
13-12-2024 21:00 - 22:00 0 MW
6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:
08:00-09:00 Network Security 17:00-18:00 Network Security 18:00-19:00 Network Security 19:00-20:00 Network Security 20:00-21:00 Network Security 21:00-22:00 Network Security7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)*?
The available remedial actions were assessed as insufficient or ineffective to avoid the violation of operational security limits