Capacity Curtailment on the ES-FR border for delivery period 10-02-2025

Published:

1. TSO(s)*:

RTE, REE

2. Identification of affected Long Term Transmission Rights:

ES-FR

3. Triggering event:

Curtailment to ensure operation remains within Operational Security Limits

4. Affected volume in MW / hour for each concerned period:

10-02-2025 19:00 - 20:00 1940 MW

10-02-2025 20:00 - 21:00 1940 MW

10-02-2025 21:00 - 22:00 1940 MW

10-02-2025 22:00 - 23:00 1940 MW

5. Amount of LTTR remaining after curtailment:

10-02-2025 19:00 - 20:00 1411 MW

10-02-2025 20:00 - 21:00 1028 MW

10-02-2025 21:00 - 22:00 1626 MW

10-02-2025 22:00 - 23:00 1154 MW

6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:

19:00-20:00 Network Security

20:00-21:00 Network Security

21:00-22:00 Network Security

22:00-23:00 Network Security

7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) ? :

The available remedial actions were assessed as insufficient or ineffective to avoid the violation of operational security limits

*According to section 57.3 of the EU HAR, this field can be filled in within 24 hours after the initial publication