Capacity Curtailment on the ES-FR border for delivery period 03/03/2026
1. TSO(s)*:
RTE-TSO
2. Identification of affected Long Term Transmission Rights:
ES-FR
3, Triggering event:
Curtailment to ensure operation remains within Operational Security Limits
4. Affected volume in MW / period:
03-03-2026 15:00 - 16:00 1830 MW
03-03-2026 16:00 - 17:00 1830 MW
03-03-2026 17:00 - 18:00 1830 MW
5. Amount of LTTR remaining after curtailment:
03-03-2026 15:00 - 16:00 767 MW
03-03-2026 16:00 - 17:00 767 MW
03-03-2026 17:00 - 18:00 767 MW
6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:
15:00-16:00 Network Security
16:00-17:00 Network Security
17:00-18:00 Network Security
7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)*?
The available remedial actions were assessed as insufficient or ineffective to avoid the violation of operational security limits