Capacity Curtailment on the ES>FR border for delivery day 24/12/2021

Published:

1. TSO(s) :

   RTE, REE

2. Identification of affected Long Term Transmission Rights

   ES->FR

3. Triggering event :

   Curtailment to ensure operation remains within Operational Security Limits

4. Affected volume in MW / hour for each concerned period :

   25/12/2021

      03:00-04:00 1670.0 MW

      04:00-05:00 1670.0 MW

      05:00-06:00 1670.0 MW

      06:00-07:00 1670.0 MW

      07:00-08:00 1670.0 MW

5. Amount of LTTR remaining after curtailment :

   25/12/2021

      03:00-04:00 1450 MW

      04:00-05:00 1450 MW

      05:00-06:00 1450 MW

      06:00-07:00 1450 MW

      07:00-08:00 1450 MW

6. Information on exact operational limit(s) that are expected to be violated in the absence of curtailment :

   25/12/2021

      03:00-04:00 Network Security

      04:00-05:00 Network Security

      05:00-06:00 Network Security

      06:00-07:00 Network Security

      07:00-08:00 Network Security

7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) ? :

   The available remedial actions were assessed as insufficient or ineffective to avoid the violation of operational security limits