Capacity Curtailment on FR-CH and CH-IT borders for delivery day 03/10/2019

Published:

Dear Market Participants,

The long-term allocated capacities for delivery date 03/10/2019 on the corridor from France to Switzerland and Switzerland to Italy has been curtailed to ensure operation remains within Operational Security Limits.

FR>CH:

From position 1 to 24 it was reduced by 50%

CH>IT:

Position 9 reduced by 1%

From position 19 to 20 reduced by 1%

Please consider the latest version of the programming authorizations.

Best regards,

Operations Team

JAO S.A.

2 rue de Bitbourg

L-1273 Luxembourg-Hamm

T. +352 27 62 38 38

Image removed.

Attachments
image002.jpg