Capacity Curtailment on the FR-ES border for delivery date 03-08-2024

Published:

1. TSO(s)*:

RTE, REE

2. Identification of affected Long Term Transmission Rights:

FR-ES

3. Triggering event:

Curtailment to ensure operation remains within Operational Security Limits

4. Affected volume in MW / hour for each concerned period:

03-08-2024 08:00 - 09:00 810 MW

03-08-2024 09:00 - 10:00 810 MW

03-08-2024 10:00 - 11:00 810 MW

03-08-2024 11:00 - 12:00 810 MW

03-08-2024 12:00 - 13:00 810 MW

03-08-2024 13:00 - 14:00 810 MW

03-08-2024 14:00 - 15:00 810 MW

03-08-2024 15:00 - 16:00 810 MW

03-08-2024 16:00 - 17:00 810 MW

03-08-2024 17:00 - 18:00 810 MW

03-08-2024 18:00 - 19:00 810 MW

03-08-2024 19:00 - 20:00 810 MW

03-08-2024 20:00 - 21:00 810 MW

03-08-2024 21:00 - 22:00 810 MW

03-08-2024 22:00 - 23:00 810 MW

03-08-2024 23:00 - 24:00 810 MW

5. Amount of LTTR remaining after curtailment:

03-08-2024 08:00 - 09:00 585 MW

03-08-2024 09:00 - 10:00 585 MW

03-08-2024 10:00 - 11:00 585 MW

03-08-2024 11:00 - 12:00 585 MW

03-08-2024 12:00 - 13:00 585 MW

03-08-2024 13:00 - 14:00 585 MW

03-08-2024 14:00 - 15:00 585 MW

03-08-2024 15:00 - 16:00 585 MW

03-08-2024 16:00 - 17:00 585 MW

03-08-2024 17:00 - 18:00 585 MW

03-08-2024 18:00 - 19:00 585 MW

03-08-2024 19:00 - 20:00 585 MW

03-08-2024 20:00 - 21:00 585 MW

03-08-2024 21:00 - 22:00 585 MW

03-08-2024 22:00 - 23:00 585 MW

03-08-2024 23:00 - 24:00 585 MW

6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:

03/08/2024
      08:00-09:00 Network Security
      09:00-10:00 Network Security
      10:00-11:00 Network Security
      11:00-12:00 Network Security
      12:00-13:00 Network Security
      13:00-14:00 Network Security
      14:00-15:00 Network Security
      15:00-16:00 Network Security
      16:00-17:00 Network Security
      17:00-18:00 Network Security
      18:00-19:00 Network Security
      19:00-20:00 Network Security
      20:00-21:00 Network Security
      21:00-22:00 Network Security
      22:00-23:00 Network Security
      23:00-24:00 Network Security

7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)*?

The available remedial actions were assessed as insufficient or ineffective to avoid the violation of operational security limits

*According to section 57.3 of the EU HAR, this field can be filled in within 24 hours after the initial publication