Capacity Curtailment on the FR-ES border for delivery day 17/05/2020

Published:

Dear Market Participants,

The long-term allocated capacities for delivery date 17/05/2020 on the corridor from France to Spain have been curtailed to ensure operation remains within Operational Security Limits.

FR>ES
From position 4 to 8 it was reduced to 1179 MW

From position 9 to 12 it was reduced to 1775 MW

From position 18 to 24 it was reduced to 1532 MW

Please consider the latest version of the programming authorizations.

Best regards,

JAO Operations Team