Capacity Curtailment on the FR-ES border for delivery day 16/10/2021
Published:
Dear Market Participants,
The long-term allocated capacities for delivery date 16/10/2021 on the corridor from France to Spain have been curtailed to ensure operation remains within Operational Security Limits.
FR>ES
From position 1 to 3 it was reduced to 1428 MW
From position 4 to 8 it was reduced to 1376 MW
From position 15 to 19 it was reduced to 1428 MW
Please consider the latest version of the programming authorizations.
Best regards,
Operations Team