Capacity Curtailment on the FR-ES border for delivery day 20/12/2021

Published:

1. TSO(s) :

   RTE, REE

2. Identification of affected Long Term Transmission Rights

   FR->ES

3. Triggering event :

   Curtailment to ensure operation remains within Operational Security Limits

4. Affected volume in MW / hour for each concerned period :

   20/12/2021

      07:00-08:00 1940.0 MW

      08:00-09:00 1940.0 MW

      09:00-10:00 1940.0 MW

      10:00-11:00 1940.0 MW

      11:00-12:00 1940.0 MW

      12:00-13:00 1940.0 MW

      13:00-14:00 1940.0 MW

      14:00-15:00 1940.0 MW

      15:00-16:00 1940.0 MW

      16:00-17:00 1940.0 MW

5. Amount of LTTR remaining after curtailment :

   20/12/2021

      07:00-08:00 1600 MW

      08:00-09:00 1600 MW

      09:00-10:00 1600 MW

      10:00-11:00 1600 MW

      11:00-12:00 1600 MW

      12:00-13:00 1600 MW

      13:00-14:00 1600 MW

      14:00-15:00 1600 MW

      15:00-16:00 1600 MW

      16:00-17:00 1600 MW

6. Information on exact operational limit(s) that are expected to be violated in the absence of curtailment :

   20/12/2021

      07:00-08:00 GAUDIERE-TAMAREAU 1

      08:00-09:00 GAUDIERE-TAMAREAU 1

      09:00-10:00 GAUDIERE-TAMAREAU 1

      10:00-11:00 GAUDIERE-TAMAREAU 1

      11:00-12:00 GAUDIERE-TAMAREAU 1

      12:00-13:00 GAUDIERE-TAMAREAU 1

      13:00-14:00 GAUDIERE-TAMAREAU 1

      14:00-15:00 GAUDIERE-TAMAREAU 1

      15:00-16:00 GAUDIERE-TAMAREAU 1

      16:00-17:00 GAUDIERE-TAMAREAU 1

7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) ? :

   The available remedial actions were assessed as insufficient or ineffective to avoid the violation of operational security limits