Capacity Curtailment on the FR-ES border for delivery day 15/10/2022

Published:

1. TSO(s) :

   RTE, REE

2. Identification of affected Long Term Transmission Rights

   FR->ES

3. Triggering event :

   Curtailment to ensure operation remains within Operational Security Limits

4. Affected volume in MW / hour for each concerned period :

   15/10/2022

      14:00-15:00 2340.0 MW

      15:00-16:00 2340.0 MW

      16:00-17:00 2340.0 MW

      17:00-18:00 2340.0 MW

      18:00-19:00 2340.0 MW

5. Amount of LTTR remaining after curtailment :

   15/10/2022

      14:00-15:00 50 MW

      15:00-16:00 50 MW

      16:00-17:00 50 MW

      17:00-18:00 50 MW

      18:00-19:00 50 MW

6. Information on exact operational limit(s) that are expected to be violated in the absence of curtailment :

   15/10/2022

      14:00-15:00 Network Security

      15:00-16:00 Network Security

      16:00-17:00 Network Security

      17:00-18:00 Network Security

      18:00-19:00 Network Security

7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) ? :

   The available remedial actions were assessed as insufficient or ineffective to avoid the violation of operational security limits