Capacity Curtailment on the FR-ES border for delivery period 02-12-2024

Published:

1. TSO(s)*:

RTE, REE

2. Identification of affected Long Term Transmission Rights:

FR-ES

3. Triggering event:

Curtailment to ensure operation remains within Operational Security Limits

4. Affected volume in MW / hour for each concerned period:

02-12-2024 09:00 - 10:00 2450 MW

02-12-2024 10:00 - 11:00 2450 MW

02-12-2024 11:00 - 12:00 2450 MW

02-12-2024 12:00 - 13:00 2450 MW

02-12-2024 13:00 - 14:00 2450 MW

02-12-2024 14:00 - 15:00 2450 MW

02-12-2024 15:00 - 16:00 2450 MW

02-12-2024 16:00 - 17:00 2450 MW

02-12-2024 17:00 - 18:00 2450 MW

5. Amount of LTTR remaining after curtailment:

02-12-2024 09:00 - 10:00 1979 MW

02-12-2024 10:00 - 11:00 1979 MW

02-12-2024 11:00 - 12:00 2025 MW

02-12-2024 12:00 - 13:00 2025 MW

02-12-2024 13:00 - 14:00 2025 MW

02-12-2024 14:00 - 15:00 2025 MW

02-12-2024 15:00 - 16:00 1917 MW

02-12-2024 16:00 - 17:00 1917 MW

02-12-2024 17:00 - 18:00 1917 MW

6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:

02/12/2024

      09:00-10:00 Network Security

      10:00-11:00 Network Security

      11:00-12:00 Network Security

      12:00-13:00 Network Security

      13:00-14:00 Network Security

      14:00-15:00 Network Security

      15:00-16:00 Network Security

      16:00-17:00 Network Security

      17:00-18:00 Network Security

7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)*?

The available remedial actions were assessed as insufficient or ineffective to avoid the violation of operational security limits