Capacity Curtailment on the FR-ES border for delivery period 24-07-2025

Published:

Dear Market Participants,

1. TSO(s)*:

RTE, REE

 

2. Identification of affected Long Term Transmission Rights:

FR->ES

 

3. Triggering event:

Curtailment to ensure operation remains within Operational Security Limits

4. Affected volume in MW / hour for each concerned period:

24-07-2025 00:00 - 01:00 1500 MW

24-07-2025 01:00 - 02:00 1500 MW

24-07-2025 02:00 - 03:00 1500 MW

24-07-2025 03:00 - 04:00 1500 MW

24-07-2025 04:00 - 05:00 1500 MW

24-07-2025 05:00 - 06:00 1500 MW

24-07-2025 06:00 - 07:00 1500 MW

24-07-2025 07:00 - 08:00 1500 MW

24-07-2025 18:00 - 19:00 1500 MW

24-07-2025 19:00 - 20:00 1500 MW

24-07-2025 20:00 - 21:00 1500 MW

24-07-2025 21:00 - 22:00 1500 MW

24-07-2025 22:00 - 23:00 1500 MW

24-07-2025 23:00 - 24:00 1500 MW

5. Amount of LTTR remaining after curtailment:

24-07-2025 00:00 - 01:00 1075 MW

24-07-2025 01:00 - 02:00 1075 MW

24-07-2025 02:00 - 03:00 1075 MW

24-07-2025 03:00 - 04:00 1075 MW

24-07-2025 04:00 - 05:00 1075 MW

24-07-2025 05:00 - 06:00 1075 MW

24-07-2025 06:00 - 07:00 1075 MW

24-07-2025 07:00 - 08:00 1075 MW

24-07-2025 18:00 - 19:00 1075 MW

24-07-2025 19:00 - 20:00 1075 MW

24-07-2025 20:00 - 21:00 1075 MW

24-07-2025 21:00 - 22:00 1075 MW

24-07-2025 22:00 - 23:00 1075 MW

24-07-2025 23:00 - 24:00 1075 MW

6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:      00:00-01:00 marsillon-pragneres 1
     01:00-02:00 marsillon-pragneres 1
     02:00-03:00 marsillon-pragneres 1
     03:00-04:00 marsillon-pragneres 1
     04:00-05:00 marsillon-pragneres 1
     05:00-06:00 marsillon-pragneres 1
     06:00-07:00 marsillon-pragneres 1
     07:00-08:00 marsillon-pragneres 1
     18:00-19:00 marsillon-pragneres 1
     19:00-20:00 marsillon-pragneres 1
     20:00-21:00 marsillon-pragneres 1
     21:00-22:00 marsillon-pragneres 1
     22:00-23:00 marsillon-pragneres 1
     23:00-24:00 marsillon-pragneres 1
 

7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)*?
   The available remedial actions were assessed as insufficient or ineffective to avoid the violation of operational security limits