Capacity Curtailment on the FR-ES border for delivery period 22-08-2025

Published:

1. TSO(s)*:

RTE, REE

2. Identification of affected Long Term Transmission Rights:

   FR->ES

3. Triggering event:

Curtailment to ensure operation remains within Operational Security Limits

4. Affected volume in MW / hour for each concerned period:

22-08-2025 04:00 - 05:00 1669 MW

22-08-2025 05:00 - 06:00 1669 MW

5. Amount of LTTR remaining after curtailment:

22-08-2025 04:00 - 05:00 869 MW

22-08-2025 05:00 - 06:00 869 MW

6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:
   22/08/2025

      04:00-05:00 Network Security

      05:00-06:00 Network Security

7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)*?
The available remedial actions were assessed as insufficient or ineffective to avoid the violation of operational security limits

*According to section 57.3 of the EU HAR, this field can be filled in within 24 hours after the initial publication