Capacity Curtailment on the FR-ES border for delivery period 21-09-2025

Published:

1. TSO(s)*:

RTE, REE

2. Identification of affected Long Term Transmission Rights:

FR-ES

3. Triggering event:

Curtailment to ensure operation remains within Operational Security Limits

4. Affected volume in MW / hour for each concerned period:

21-09-2025 19:00 - 20:00 1620 MW

21-09-2025 20:00 - 21:00 1620 MW

21-09-2025 21:00 - 22:00 1620 MW

21-09-2025 22:00 - 23:00 1620 MW

21-09-2025 23:00 - 24:00 1620 MW

5. Amount of LTTR remaining after curtailment:

21-09-2025 19:00 - 20:00 1219 MW

21-09-2025 20:00 - 21:00 1219 MW

21-09-2025 21:00 - 22:00 1219 MW

21-09-2025 22:00 - 23:00 1219 MW

21-09-2025 23:00 - 24:00 1219 MW

6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:

Network Security

7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)*?

The available remedial actions were assessed as insufficient or ineffective to avoid the violation of operational security limits