Capacity Curtailment on FR-IT and NL-DE border for delivery day 13/09/2019
Dear Market Participants,
The long-term allocated capacities for delivery date 13/09/2019 on the corridor from France to Italy and from The Netherlands to Germany have been curtailed to ensure operation remains within Operational Security Limits.
FR>IT:
From position 1 to 7 it was reduced to 1355 MW.
From position 8 and 9 it was reduced to 1599 MW.
From position 10 to 12 it was reduced to 1491 MW.
From position 13 to 17 it was reduced to 1599 MW.
From position 18 to 23 it was reduced to 1577 MW.
Position 24 was reduced to 1376
NL>DE:
Position 23 was reduced to 899
Please consider the latest version of the programming authorizations.
Best regards,
Operations Team
JAO S.A.
2 rue de Bitbourg
L-1273 Luxembourg-Hamm
T. +352 27 62 38 38