Capacity Curtailment on the FR-IT border for 28th of July

Published:

1. TSO(s) *: TERNA

2. Identification of affected Long Term Transmission Rights

France to Italy

3. Triggering event:

☒Curtailment to ensure operation remains within Operational Security Limits
☐Curtailment due to Force Majeure
☐Curtailment due to emergency situation

4. Affected volume in MW / hour for each concerned period:

France to Italy

28/07/2020

00:00 – 01:00 2051 MW

01:00 – 02:00 2051 MW

02:00 – 03:00 2051 MW

03:00 – 04:00 2051 MW

04:00 – 05:00 2051 MW

05:00 – 06:00 2051 MW

06:00 – 07:00 2051 MW

5. Amount of LTTR remaining after curtailment:

France to Italy

28/07/2020

00:00 – 01:00 1971 MW

01:00 – 02:00 1971 MW

02:00 – 03:00 1971 MW

03:00 – 04:00 1971 MW

04:00 – 05:00 1971 MW

05:00 – 06:00 1971 MW

06:00 – 07:00 1971 MW

6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment *:

Voltage stability issue on the Italian Electrical system.

7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?

During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC in the calculation.

Kind regards,

Gabriele ARNOLDI

Capacity Allocation Specialist

JAO S.A.

2 rue de Bitbourg

L-1273 Luxembourg-Hamm

T. +352 27 62 38 38

Visit us at www.jao.eu

Follow us on LinkedIn

Image removed.


Servicing TSOs and facilitating electricity markets since 2008