Capacity curtailment on FR-IT border for delivery date 20/03/2020
Published:
Swissgrid
FR-IT
☒Curtailment to ensure operation remains within Operational Security Limits
☐Curtailment due to Force Majeure
☐Curtailment due to emergency situation
20/03/2020
12:00 – 13:00 2487 MW
13:00 – 14:00 2487 MW
14:00 – 15:00 2487 MW
20/03/2020
12:00 – 13:00 2251 MW
13:00 – 14:00 2251 MW
14:00 – 15:00 2251 MW
Reduction due to expected overloads on 220kV Riddes-Valpelline (110 %)
During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC in the calculation.
-*According to section 57.3 of the EU HAR, this field can be filled in within 24 hours after the initial publication