Capacity Curtailment on the FR-IT border for delivery date 01-07-2024
1. TSO(s)*:
TERNA
2. Identification of affected Long Term Transmission Rights:
FR-IT
3. Triggering event:
Curtailment to ensure operation remains within Operational Security Limits
4. Affected volume in MW / hour for each concerned period:
01-07-2024 01:00 - 02:00 2816 MW
01-07-2024 02:00 - 03:00 2816 MW
01-07-2024 03:00 - 04:00 2816 MW
01-07-2024 04:00 - 05:00 2816 MW
01-07-2024 15:00 - 16:00 2816 MW
01-07-2024 16:00 - 17:00 2816 MW
01-07-2024 17:00 - 18:00 2816 MW
01-07-2024 18:00 - 19:00 2816 MW
01-07-2024 19:00 - 20:00 2816 MW
01-07-2024 20:00 - 21:00 2816 MW
01-07-2024 23:00 - 24:00 2816 MW
5. Amount of LTTR remaining after curtailment:
01-07-2024 01:00 - 02:00 2699 MW
01-07-2024 02:00 - 03:00 2645 MW
01-07-2024 03:00 - 04:00 2509 MW
01-07-2024 04:00 - 05:00 2645 MW
01-07-2024 15:00 - 16:00 2340 MW
01-07-2024 16:00 - 17:00 2340 MW
01-07-2024 17:00 - 18:00 2340 MW
01-07-2024 18:00 - 19:00 2591 MW
01-07-2024 19:00 - 20:00 2591 MW
01-07-2024 20:00 - 21:00 2591 MW
01-07-2024 23:00 - 24:00 2680 MW
6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:
Expected violation of operational security limits of physical transmission assets
7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)*?
During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC in the calculation