Capacity Curtailment on the FR-IT border for delivery day 11/02/2021
1. TSO(s) *: TERNA; RTE, SWISSGRID; APG; ELES
2. Identification of affected Long Term Transmission Rights
France to Italy
3. Triggering event:
☒Curtailment to ensure operation remains within Operational Security Limits
☐Curtailment due to Force Majeure
☐Curtailment due to emergency situation
4. Affected volume in MW / hour for each concerned period:
France to Italy
11/02/2021
• 23:00 - 24:00 2487 MW
5. Amount of LTTR remaining after curtailment:
France to Italy
11/02/2021
• 23:00 - 24:00 2432 MW
6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment *:
N-2 DIVACA-REDIPUGLIA+DIVACA-PADRICIANO: Lienz-Soverzene
7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *? During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC in the calculation.