Capacity Curtailment on the FR-IT border for delivery day 15/02/2021

Published:

1.       TSO(s) *: TERNA, RTE, Swissgrid, APG, ELES

2.       Identification of affected Long Term Transmission Rights

          France to Italy

3.       Triggering event:

☒Curtailment to ensure operation remains within Operational Security Limits
☐Curtailment due to Force Majeure
☐Curtailment due to emergency situation
 

4.       Affected volume in MW / hour for each concerned period:

         France to Italy

15/02/2021 

         • 23:00 - 24:00 2487 MW

 

5.       Amount of LTTR remaining after curtailment:

         France to Italy

15/02/2021  

         • 23:00 - 24:00 2432 MW

            

6.       Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment *:  

         Reduction due to the following overloaded element(s):  Lienz-Soverzene (126,3%)

7.       Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?

During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC in the calculation