Capacity Curtailment on the FR-IT border for delivery day 25/04/2021

Published:

1.TSO(s) *:   TERNA

2. Identification of affected Long Term Transmission Rights

France to Italy

3. Triggering event:

 

☒Curtailment to ensure operation remains within Operational Security Limits
☐Curtailment due to Force Majeure
☐Curtailment due to emergency situation
 

4. Affected volume in MW / hour for each concerned period:

France to Italy

25/04/2021  

 

10:00 – 11:00  303 MW

11:00 – 12:00  303 MW

12:00 – 13:00  303 MW

13:00 – 14:00  303 MW

14:00 – 15:00  303 MW

15:00 – 16:00  303 MW

16:00 – 17:00  303 MW

 

5. Amount of LTTR remaining after curtailment:

France to Italy

25/04/2021  

 

10:00 – 11:00  0 MW

11:00 – 12:00  0 MW

12:00 – 13:00  0 MW

13:00 – 14:00  0 MW

14:00 – 15:00  0 MW

15:00 – 16:00  0 MW

16:00 – 17:00  0 MW

 

6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment *:

    Voltage stability issue on the Italian Electrical system

 

7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?

    During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC in the calculation