Capacity Curtailment on the FR-IT border for delivery day 01/10/2021

Published:

1.TSO(s) *:

TERNA, RTE, Swissgrid, APG, ELES

2. Identification of affected Long Term Transmission Rights

France to Italy

3. Triggering event:

☒Curtailment to ensure operation remains within Operational Security Limits
☐Curtailment due to Force Majeure
☐Curtailment due to emergency situation
 

4. Affected volume in MW / hour for each concerned period:

France to Italy

01/10/2021  

 

00:00 – 01:00  2415 MW

01:00 – 02:00  2415 MW

02:00 – 03:00  2415 MW

03:00 – 04:00  2415 MW

04:00 – 05:00  2415 MW

05:00 – 06:00  2415 MW

06:00 – 07:00  2415 MW

07:00 – 08:00  2415 MW

08:00 – 09:00  2415 MW

09:00 – 10:00  2415 MW

10:00 – 11:00  2415 MW

11:00 – 12:00  2415 MW

12:00 – 13:00  2415 MW

13:00 – 14:00  2415 MW

14:00 – 15:00  2415 MW

15:00 – 16:00  2415 MW

16:00 – 17:00  2415 MW

17:00 – 18:00  2415 MW

18:00 – 19:00  2415 MW

19:00 – 20:00  2415 MW

20:00 – 21:00  2415 MW

21:00 – 22:00  2415 MW

22:00 – 23:00  2415 MW

23:00 – 24:00  2415 MW 

 

5. Amount of LTTR remaining after curtailment:

France to Italy

01/10/2021

 

00:00 – 01:00  2415 MW

01:00 – 02:00  2415 MW

02:00 – 03:00  2415 MW

03:00 – 04:00  2415 MW

04:00 – 05:00  2415 MW

05:00 – 06:00  2415 MW

06:00 – 07:00  2415 MW

07:00 – 08:00  2415 MW

08:00 – 09:00  2415 MW

09:00 – 10:00  2415 MW

10:00 – 11:00  2415 MW

11:00 – 12:00  1876 MW

12:00 – 13:00  1876 MW

13:00 – 14:00  1876 MW

14:00 – 15:00  2415 MW

15:00 – 16:00  2415 MW

16:00 – 17:00  2415 MW

17:00 – 18:00  2415 MW

18:00 – 19:00  2415 MW

19:00 – 20:00  2415 MW

20:00 – 21:00  2415 MW

21:00 – 22:00  2415 MW

22:00 – 23:00  2415 MW

23:00 – 24:00  2415 MW 

 

6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment *:

Reduction due to the following overloaded element(s): 220kV Riddes - Valpelline; 380/220kV Lavorgo; 380kV Lavorgo - Musignano; 380kV Bulciago - Soazza; 220kV Avise - Riddes; 380kV Sils – Soazza; Lienz – Soverzene.

7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?

During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC in the calculation