Capacity Curtailment on the FR-IT border for delivery day 15/10/2021
1.TSO(s) *:
Swissgrid
2. Identification of affected Long Term Transmission Rights
France to Italy
3. Triggering event:
☒Curtailment to ensure operation remains within Operational Security Limits
☐Curtailment due to Force Majeure
☐Curtailment due to emergency situation
4. Affected volume in MW / hour for each concerned period:
France to Italy
15/10/2021
21:00 – 22:00 2415 MW
22:00 – 23:00 2415 MW
23:00 – 24:00 2415 MW
5. Amount of LTTR remaining after curtailment:
France to Italy
15/10/2021
21:00 – 22:00 1881 MW
22:00 – 23:00 1881 MW
23:00 – 24:00 2101 MW
6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment *:
Reduction due to expected overloads on 220 kV Riddes-Valpeline
7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?
During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC in the calculation.