Capacity Curtailment on the FR-IT border for delivery day 09/12/2021

Published:

1. TSO(s)*:

2. Identification of affected Long Term Transmission Rights
FR-IT

3. Triggering event :

ý Curtailment to ensure operation remains within Operational Security Limits

o Curtailment due to Force Majeure

o Curtailment due to emergency situation

4. Affected volume in MW / hour for each concerned period:

• 09/12/2021

         • 00:00 - 01:00 1991MW

         • 01:00 - 02:00 1991MW

         • 02:00 - 03:00 1991MW

         • 03:00 - 04:00 1991MW

         • 04:00 - 05:00 1991MW

         • 05:00 - 06:00 1991MW

         • 06:00 - 07:00 1991MW

         • 07:00 - 08:00 1991MW

         • 08:00 - 09:00 1991MW

         • 09:00 - 10:00 1991MW

         • 10:00 - 11:00 1991MW

         • 11:00 - 12:00 1991MW

         • 12:00 - 13:00 1991MW

         • 13:00 - 14:00 1991MW

         • 14:00 - 15:00 1991MW

         • 15:00 - 16:00 1991MW

         • 16:00 - 17:00 1991MW

         • 17:00 - 18:00 1991MW

         • 18:00 - 19:00 1991MW

         • 19:00 - 20:00 1991MW

         • 21:00 - 22:00 1991MW

         • 22:00 - 23:00 1991MW

         • 23:00 - 24:00 1991MW


5. Amount of LTTR remaining after curtailment:

• 09/12/2021

         • 00:00 - 01:00 1991MW

         • 01:00 - 02:00 1906MW

         • 02:00 - 03:00 1607MW

         • 03:00 - 04:00 1502MW

         • 04:00 - 05:00 1703MW

         • 05:00 - 06:00 1991MW

         • 06:00 - 07:00 1991MW

         • 07:00 - 08:00 1991MW

         • 08:00 - 09:00 1991MW

         • 09:00 - 10:00 1991MW

         • 10:00 - 11:00 1991MW

         • 11:00 - 12:00 1991MW

         • 12:00 - 13:00 1991MW

         • 13:00 - 14:00 1991MW

         • 14:00 - 15:00 1991MW

         • 15:00 - 16:00 1991MW

         • 16:00 - 17:00 1991MW

         • 17:00 - 18:00 1991MW

         • 18:00 - 19:00 1991MW

         • 19:00 - 20:00 1991MW

         • 21:00 - 22:00 1991MW

         • 22:00 - 23:00 1991MW

         • 23:00 - 24:00 1991MW


6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:


7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?

Kind regards,

Operations Team