Capacity Curtailment on the FR-IT border for delivery day 24/09/2022

Published:

1.TSO(s) *: TERNA

2. Identification of affected Long Term Transmission Rights

France to Italy

3. Triggering event:

 

☒Curtailment to ensure operation remains within Operational Security Limits
☐Curtailment due to Force Majeure
☐Curtailment due to emergency situation
 

4. Affected volume in MW / hour for each concerned period:

France to Italy

24/09/2022  

 

13:00 – 14:00  2061 MW

14:00 – 15:00  2061 MW

 

5. Amount of LTTR remaining after curtailment:

France to Italy

24/09/2022  

 

13:00 – 14:00  1997 MW

14:00 – 15:00  1997 MW

 

6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment *:

Expected violation of operational security limits of physical transmission assets.

7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?

 During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC in the calculation.