The long-term allocated capacities for delivery date 19/10/2019 on corridor from France to Italy have been curtailed to ensure operation remains within Operational Security Limits.

FR>IT

On positions 13-16 it was reduced to 2330 MW

Please consider the latest version of the programming authorizations.