Capacity Curtailment on the FR-IT border for delivery day 25/08/2020

Published:

1.       TSO(s) *: TERNA

2.       Identification of affected Long Term Transmission Rights

          France to Italy

3.       Triggering event:

 

☐Curtailment to ensure operation remains within Operational Security Limits
☐Curtailment due to Force Majeure
☐Curtailment due to emergency situation
 

4.       Affected volume in MW / hour for each concerned period:

         France to Italy

25/08/2020  

 

00:00 – 01:00  2051 MW

01:00 – 02:00  2051 MW

02:00 – 03:00  2051 MW

 

5.       Amount of LTTR remaining after curtailment:

         France to Italy

25/08/2020  

 

00:00 – 01:00  1764 MW

01:00 – 02:00  1764 MW

02:00 – 03:00  1764 MW

          

6.       Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment *:  

 Voltage stability issue on the Italian Electrical system.

          

7.       Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?

 During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC in the calculation.