Capacity Curtailment on the FR-IT border for delivery day 17/09/2020
1. TSO(s) *: TERNA; RTE, SWISSGRID; APG; ELES
2. Identification of affected Long Term Transmission Rights
France to Italy
3. Triggering event :
☒Curtailment to ensure operation remains within Operational Security Limits
☐Curtailment due to Force Majeure
☐Curtailment due to emergency situation
4. Affected volume in MW / hour for each concerned period :
France to Italy
17/09/2020
18:00 – 19:00 2051 MW
19:00 – 20:00 2051 MW
20:00 – 21:00 2051 MW
23:00 – 24:00 2051 MW
5. Amount of LTTR remaining after curtailment :
France to Italy
17/09/2020
18:00 – 19:00 1949 MW
19:00 – 20:00 1949 MW
20:00 – 21:00 1949 MW
23:00 – 24:00 1947 MW
<6.Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment *:
Reduction due to expected overloads on 380-kV-Fiorano-Robbia
During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC in the calculation