Capacity Curtailment on the FR-IT border for delivery day 19/09/2020
1. TSO(s) *: TERNA; RTE, SWISSGRID; APG; ELES
2. Identification of affected Long Term Transmission Rights
France to Italy
3. Triggering event:
☒Curtailment to ensure operation remains within Operational Security Limits
☐Curtailment due to Force Majeure
☐Curtailment due to emergency situation
4. Affected volume in MW / hour for each concerned period:
France to Italy
19/09/2020
03:00 – 04:00 2051 MW
04:00 – 05:00 2051 MW
05:00 – 06:00 2051 MW
06:00 – 07:00 2051 MW
23:00 – 24:00 2051 MW
5. Amount of LTTR remaining after curtailment :
France to Italy
19/09/2020
03:00 – 04:00 1903 MW
04:00 – 05:00 1903 MW
05:00 – 06:00 1903 MW
06:00 – 07:00 1903 MW
23:00 – 24:00 1798 MW
6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment *:
Reduction due to expected overloads on Lienz-Soverzene
7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?
During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC in the calculation