Capacity Curtailment on the FR-IT border for delivery period 17-09-2024
1. TSO(s)*:
TERNA
2. Identification of affected Long Term Transmission Rights:
FR-IT
3. Triggering event:
Curtailment to ensure operation remains within Operational Security Limits
4. Affected volume in MW / hour for each concerned period:
17-09-2024 12:00 - 13:00 2032 MW
17-09-2024 13:00 - 14:00 2032 MW
17-09-2024 14:00 - 15:00 2032 MW
17-09-2024 15:00 - 16:00 2032 MW
17-09-2024 16:00 - 17:00 2032 MW
17-09-2024 17:00 - 18:00 2032 MW
17-09-2024 18:00 - 19:00 2032 MW
17-09-2024 19:00 - 20:00 2032 MW
17-09-2024 20:00 - 21:00 2032 MW
17-09-2024 23:00 - 24:00 2032 MW
5. Amount of LTTR remaining after curtailment:
17-09-2024 12:00 - 13:00 1800 MW
17-09-2024 13:00 - 14:00 1800 MW
17-09-2024 14:00 - 15:00 1800 MW
17-09-2024 15:00 - 16:00 1938 MW
17-09-2024 16:00 - 17:00 1938 MW
17-09-2024 17:00 - 18:00 1938 MW
17-09-2024 18:00 - 19:00 1900 MW
17-09-2024 19:00 - 20:00 1900 MW
17-09-2024 20:00 - 21:00 1900 MW
17-09-2024 23:00 - 24:00 1877 MW
6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:
Expected violation of operational security limits of physical transmission assets
7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)*?
During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC in the calculation
*According to section 57.3 of the EU HAR, this field can be filled in within 24 hours after the initial publication