Capacity Curtailment on the FR-IT border for delivery period 20-09-2024

Published:

1. TSO(s):

TERNA, ELES, RTE, APG, SWISSGRID

2. Identification of affected Long Term Transmission Rights:

FR-IT

3. Triggering event:

Curtailment to ensure operation remains within Operational Security Limits

4. Affected volume in MW / hour for each concerned period:

20-09-2024 00:00 - 01:00 2032 MW

20-09-2024 01:00 - 02:00 2032 MW

20-09-2024 02:00 - 03:00 2032 MW

20-09-2024 15:00 - 16:00 2032 MW

20-09-2024 16:00 - 17:00 2032 MW

20-09-2024 20:00 - 21:00 2032 MW

20-09-2024 21:00 - 22:00 2032 MW

20-09-2024 22:00 - 23:00 2032 MW

20-09-2024 23:00 - 24:00 2032 MW

5. Amount of LTTR remaining after curtailment:

20-09-2024 00:00 - 01:00 1948 MW

20-09-2024 01:00 - 02:00 1948 MW

20-09-2024 02:00 - 03:00 1948 MW

20-09-2024 15:00 - 16:00 1479 MW

20-09-2024 16:00 - 17:00 1947 MW

20-09-2024 20:00 - 21:00 1881 MW

20-09-2024 21:00 - 22:00 1232 MW

20-09-2024 22:00 - 23:00 1232 MW

20-09-2024 23:00 - 24:00 1005 MW

6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment:

Expected violation of operational security limits of physical transmission assets

7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)?:

During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC in the calculation