Capacity Curtailment on the FR-IT border for delivery period 29-09-2024

Published:

1. TSO(s)*: TERNA, RTE

2. Identification of affected Long Term Transmission Rights:

FR-IT

3. Triggering event:

Curtailment to ensure operation remains within Operational Security Limits

4. Affected volume in MW / hour for each concerned period:

29-09-2024 08:00 - 09:00 852 MW

29-09-2024 09:00 - 10:00 852 MW

29-09-2024 10:00 - 11:00 852 MW

29-09-2024 11:00 - 12:00 852 MW

29-09-2024 12:00 - 13:00 852 MW

29-09-2024 13:00 - 14:00 852 MW

29-09-2024 14:00 - 15:00 852 MW

29-09-2024 15:00 - 16:00 852 MW

29-09-2024 16:00 - 17:00 852 MW

29-09-2024 17:00 - 18:00 852 MW

5. Amount of LTTR remaining after curtailment:

29-09-2024 08:00 - 09:00 771 MW

29-09-2024 09:00 - 10:00 501 MW

29-09-2024 10:00 - 11:00 275 MW

29-09-2024 11:00 - 12:00 29 MW

29-09-2024 12:00 - 13:00 0 MW

29-09-2024 13:00 - 14:00 0 MW

29-09-2024 14:00 - 15:00 0 MW

29-09-2024 15:00 - 16:00 0 MW

29-09-2024 16:00 - 17:00 197 MW

29-09-2024 17:00 - 18:00 607 MW

6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:

Expected violation of operational security limits of physical transmission assets

7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)*?

During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC in the calculation

*According to section 57.3 of the EU HAR, this field can be filled in within 24 hours after the initial publication