Capacity Curtailment on the FR-IT border for delivery period 01-10-2024
1. TSO(s):
TERNA/RTE
2. Identification of affected Long Term Transmission Rights:
FR-IT
3. Triggering event:
Curtailment to ensure operation remains within Operational Security Limits
4. Affected volume in MW / hour for each concerned period:
01-10-2024 00:00 - 01:00 1862 MW
01-10-2024 01:00 - 02:00 1862 MW
01-10-2024 02:00 - 03:00 1862 MW
01-10-2024 03:00 - 04:00 1862 MW
01-10-2024 04:00 - 05:00 1862 MW
01-10-2024 05:00 - 06:00 1862 MW
01-10-2024 06:00 - 07:00 1862 MW
01-10-2024 07:00 - 08:00 1862 MW
01-10-2024 08:00 - 09:00 1862 MW
01-10-2024 09:00 - 10:00 1862 MW
01-10-2024 10:00 - 11:00 1862 MW
01-10-2024 11:00 - 12:00 1862 MW
01-10-2024 12:00 - 13:00 1862 MW
01-10-2024 13:00 - 14:00 1862 MW
01-10-2024 14:00 - 15:00 1862 MW
01-10-2024 15:00 - 16:00 1862 MW
01-10-2024 16:00 - 17:00 1862 MW
01-10-2024 17:00 - 18:00 1862 MW
01-10-2024 18:00 - 19:00 1862 MW
01-10-2024 19:00 - 20:00 1862 MW
01-10-2024 20:00 - 21:00 1862 MW
01-10-2024 21:00 - 22:00 1862 MW
01-10-2024 22:00 - 23:00 1862 MW
01-10-2024 23:00 - 24:00 1862 MW
5. Amount of LTTR remaining after curtailment:
01-10-2024 00:00 - 01:00 1659 MW
01-10-2024 01:00 - 02:00 1659 MW
01-10-2024 02:00 - 03:00 1659 MW
01-10-2024 03:00 - 04:00 1659 MW
01-10-2024 04:00 - 05:00 1659 MW
01-10-2024 05:00 - 06:00 1659 MW
01-10-2024 06:00 - 07:00 1659 MW
01-10-2024 07:00 - 08:00 1659 MW
01-10-2024 08:00 - 09:00 1659 MW
01-10-2024 09:00 - 10:00 1425 MW
01-10-2024 10:00 - 11:00 1425 MW
01-10-2024 11:00 - 12:00 1425 MW
01-10-2024 12:00 - 13:00 1659 MW
01-10-2024 13:00 - 14:00 1659 MW
01-10-2024 14:00 - 15:00 1659 MW
01-10-2024 15:00 - 16:00 1659 MW
01-10-2024 16:00 - 17:00 1659 MW
01-10-2024 17:00 - 18:00 1659 MW
01-10-2024 18:00 - 19:00 1670 MW
01-10-2024 19:00 - 20:00 1670 MW
01-10-2024 20:00 - 21:00 1670 MW
01-10-2024 21:00 - 22:00 1659 MW
01-10-2024 22:00 - 23:00 1659 MW
01-10-2024 23:00 - 24:00 1587 MW
6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment:
Expected violation of operational security limits of physical transmission assets
7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)?
During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC in the calculation