Capacity Curtailment on the FR-IT border for delivery period 27-10-2024

Published:

1. TSO(s)*:

TERNA

2. Identification of affected Long Term Transmission Rights:

FR-IT

3. Triggering event:

Curtailment to ensure operation remains within Operational Security Limits

4. Affected volume in MW / hour for each concerned period:

27-10-2024 00:00 - 01:00 1862 MW

27-10-2024 01:00 - 02:00 1862 MW

27-10-2024 02:00 - 03:00 1862 MW

27-10-2024 02:00 - 03:00 1862 MW

27-10-2024 03:00 - 04:00 1862 MW

27-10-2024 04:00 - 05:00 1862 MW

27-10-2024 05:00 - 06:00 1862 MW

27-10-2024 06:00 - 07:00 1862 MW

27-10-2024 07:00 - 08:00 1862 MW

27-10-2024 08:00 - 09:00 1862 MW

27-10-2024 09:00 - 10:00 1862 MW

27-10-2024 10:00 - 11:00 1862 MW

27-10-2024 11:00 - 12:00 1862 MW

27-10-2024 12:00 - 13:00 1862 MW

27-10-2024 13:00 - 14:00 1862 MW

27-10-2024 14:00 - 15:00 1862 MW

5. Amount of LTTR remaining after curtailment:

27-10-2024 00:00 - 01:00 112 MW

27-10-2024 01:00 - 02:00 873 MW

27-10-2024 02:00 - 03:00 112 MW

27-10-2024 02:00 - 03:00 914 MW

27-10-2024 03:00 - 04:00 1499 MW

27-10-2024 04:00 - 05:00 1470 MW

27-10-2024 05:00 - 06:00 1580 MW

27-10-2024 06:00 - 07:00 1704 MW

27-10-2024 07:00 - 08:00 1401 MW

27-10-2024 08:00 - 09:00 1146 MW

27-10-2024 09:00 - 10:00 1014 MW

27-10-2024 10:00 - 11:00 535 MW

27-10-2024 11:00 - 12:00 733 MW

27-10-2024 12:00 - 13:00 945 MW

27-10-2024 13:00 - 14:00 1240 MW

27-10-2024 14:00 - 15:00 1580 MW

6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:

Expected violation of operational security limits of physical transmission assets.

7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?

During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC in the calculation.