Capacity Curtailment on the FR-IT border for delivery period 14-07-2025

Published:

1. TSO(s)*:
TERNA

2. Identification of affected Long Term Transmission Rights:
FR-IT

3. Triggering event:
Curtailment to ensure operation remains within Operational Security Limits

4. Affected volume in MW / hour for each concerned period:
14-07-2025 23:00 - 24:00 2120 MW

5. Amount of LTTR remaining after curtailment:
14-07-2025 23:00 - 24:00 2015 MW

6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:
Expected violation of operational security limits of physical transmission assets


7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)*?

During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC in the calculation