Capacity curtailment on the FR-IT border for Market Period 27/04/2020
1. TSO(s) :
TERNA
2. Identification of affected Long Term Transmission Rights
France to Italy
3. Triggering event :
☒Curtailment to ensure operation remains within Operational Security Limits
☐Curtailment due to Force Majeure
☐Curtailment due to emergency situation
4. Affected volume in MW / hour for each concerned period :
France to Italy
27/04/2020
§ 00:00 – 01:00 930 MW
§ 01:00 – 02:00 930 MW
§ 02:00 – 03:00 930 MW
§ 03:00 – 04:00 930 MW
§ 04:00 – 05:00 930 MW
§ 05:00 – 06:00 930 MW
§ 06:00 – 07:00 930 MW
§ 07:00 – 08:00 930 MW
§ 08:00 – 09:00 930 MW
§ 09:00 – 10:00 930 MW
§ 10:00 – 11:00 930 MW
§ 11:00 – 12:00 930 MW
§ 12:00 – 13:00 930 MW
§ 13:00 – 14:00 930 MW
§ 14:00 – 15:00 930 MW
§ 15:00 – 16:00 930 MW
§ 16:00 – 17:00 930 MW
5. Amount of LTTR remaining after curtailment :
France to Italy
27/04/2020
§ 00:00 – 01:00 0 MW
§ 01:00 – 02:00 0 MW
§ 02:00 – 03:00 0 MW
§ 03:00 – 04:00 0 MW
§ 04:00 – 05:00 0 MW
§ 05:00 – 06:00 565 MW
§ 06:00 – 07:00 656 MW
§ 07:00 – 08:00 634 MW
§ 08:00 – 09:00 574 MW
§ 09:00 – 10:00 574 MW
§ 10:00 – 11:00 706 MW
§ 11:00 – 12:00 688 MW
§ 12:00 – 13:00 688 MW
§ 13:00 – 14:00 688 MW
§ 14:00 – 15:00 688 MW
§ 15:00 – 16:00 688 MW
§ 16:00 – 17:00 688 MW
6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment :
Voltage stability issue on the Italian Electrical system
7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) ?
During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC in the calculation