Capacity Curtailment from France to Italy and from Austria to Italy for delivery date 02/02/2019

Published:

Dear Market Participants,

The long-term allocated capacities for delivery date 02/02/2019 on the corridor from France to Italy and from Austria to Italy have been curtailed to ensure operation remains within Operational Security Limits.

FR>IT:

Position 24 was reduced to 2372 MW

AT>IT:

Position 24 was reduced to 201 MW

Please consider the latest version of the programming authorizations.

Kind regards,

Operations Team