Capacity Curtailment from France to Italy and from Austria to Italy for delivery date 12/02/2019

Published:

Dear Market Participants,

The long-term allocated capacities for delivery date 12/02/2019 on the corridors from France to Italy and from Austria to Italy have been curtailed to ensure operation remains within Operational Security Limits.

FR>IT:

On position 24 was reduced to 2368 MW

AT>IT:

On position 24 it was reduced to 201 MW

Please consider the latest version of the programming authorizations.