Capacity Curtailment from France to Italy for delivery date 23/01/2019

Published:

Dear Market Participants,

The long-term allocated capacities for delivery date 23/01/2019 on the corridor from France to Italy have been curtailed to ensure operation remains within Operational Security Limits.

FR>IT:

From position 1 to 7 it was reduced to 2085 MW

From position 8 to 21 it was reduced to 2403 MW

On position 22 it was reduced to 1953 MW

On position 23 it was reduced to 1937MW

On position 24 it was reduced to 2085 MW

Please consider the latest version of the programming authorizations.

Kind regards,

Operations Team

JAO S.A.

2 rue de Bitbourg

L-1273 Luxembourg-Hamm

T. +352 27 62 38 38

Image removed.

Attachments
image003.jpg