Capacity Curtailment from France to Italy for delivery date 24/01/2019

Published:

Dear Market Participants,

The long-term allocated capacities for delivery date 24/01/2019 on the corridor from France to Italy have been curtailed to ensure operation remains within Operational Security Limits.

FR>IT:

From position 1 to 7 it was reduced to 2106 MW

On position 22 and position 23 it was reduced to 1953 MW

On position 24 it was reduced to 2106 MW

Please consider the latest version of the programming authorizations.

Kind regards,

Operations Team