Capacity Curtailment on the France-Spain corridor for delivery day 02/03/2020

Published:

Dear Market Participants,

The long-term allocated capacities for delivery date 02/03/2020 on the corridor from France to Spain have been curtailed to ensure operation remains within Operational Security Limits.

FR>ES
On positions 1 it was reduced to 1415 MW
From position 19 to 24 it was reduced to 1415 MW

Please consider the latest version of the programming authorizations.

Best regards,
Operations Team