Capacity curtailment on the French-Spain border for business day 16/06/2022

Published:

1. TSO(s) :

   RTE, REE

2. Identification of affected Long Term Transmission Rights

   FR->ES

3. Triggering event :

   Curtailment to ensure operation remains within Operational Security Limits

4. Affected volume in MW / hour for each concerned period :

  16/06/2022

      00:00-01:00 1320.0 MW

      01:00-02:00 1320.0 MW

      02:00-03:00 1320.0 MW

      03:00-04:00 1320.0 MW

5. Amount of LTTR remaining after curtailment :

   16/06/2022

      00:00-01:00 1100 MW

      01:00-02:00 1100 MW

      02:00-03:00 1100 MW

      03:00-04:00 1100 MW

6. Information on exact operational limit(s) that are expected to be violated in the absence of curtailment :

   16/06/2022

      00:00-01:00 Network Security

      01:00-02:00 Network Security

      02:00-03:00 Network Security

      03:00-04:00 Network Security

7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) ? :

   The available remedial actions were assessed as insufficient or ineffective to avoid the violation of operational security limits