Capacity Curtailment on the FR<>ES border for delivery day 22/03/2022
Published:
1. TSO(s) :
RTE, REE
2. Identification of affected Long Term Transmission Rights
FR->ES
3. Triggering event :
Curtailment to ensure operation remains within Operational Security Limits
4. Affected volume in MW / hour for each concerned period :
22/03/2022
17:00-18:00 2120.0 MW
18:00-19:00 2120.0 MW
19:00-20:00 2120.0 MW
20:00-21:00 2120.0 MW
21:00-22:00 2120.0 MW
22:00-23:00 2120.0 MW
23:00-24:00 2120.0 MW
5. Amount of LTTR remaining after curtailment :
22/03/2022
17:00-18:00 2050 MW
18:00-19:00 2050 MW
19:00-20:00 2050 MW
20:00-21:00 2050 MW
21:00-22:00 2050 MW
22:00-23:00 2050 MW
23:00-24:00 2050 MW
6. Information on exact operational limit(s) that are expected to be violated in the absence of curtailment :
22/03/2022
17:00-18:00 Network Security
18:00-19:00 Network Security
19:00-20:00 Network Security
20:00-21:00 Network Security
21:00-22:00 Network Security
22:00-23:00 Network Security
23:00-24:00 Network Security
7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) ? :
The available remedial actions were assessed as insufficient or ineffective to avoid the violation of operational security limits