Capacity Curtailment on the GB>NL and NL>GB border for delivery day 08/07/2020

Published:

TSO(s) *:

BritNed Development Limited

Identification of affected Long Term Transmission Rights

BDL GB-NL

BDL NL-GB

Triggering event :

Curtailment to ensure operation remains within Operational Security Limits


Affected volume in MW / hour for each concerned period :

[MW before curtailment info splitted by day / hour CET/CEST]

683MW GB -NL 08/07/2020 00:00 – 09/07/2020 00:00

667MW NL-GB 08/07/2020 00:00 – 09/07/2020 00:00

Amount of LTTR remaining after curtailment :

[After curtailment info splitted by day / hour CET/CEST]

508 MW GB -NL 08/07/2020 00:00 – 09/07/2020 00:00

508 MW NL-GB 08/07/2020 00:00 – 09/07/2020 00:00

Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment *:

voltage limits, short-circuit current limits, frequency and dynamic stability limits

Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?
No other re-dispatch possibilities.