Capacity Curtailment from Germany to Denmark-2 and Denmark-2 to Germany for delivery date 02, 03, 04 and 05 of May 2018

Published:

Dear Market Participants,

The long-term allocated capacity for delivery date 02, 03, 04 and 05 of May 2018 on the corridor from Germany to Denmark-2 and Denmark-2 to Germany has been curtailed to ensure operation remains within Operational Security Limits.

DE>D2:


On 02.05.2018

From position 09 to position 18 reduced to 0 MW

On 03.05.2018

From position 07 to position 18 reduced to 0 MW

On 04.05.2018

From position 07 to position 18 reduced to 0 MW

On 05.05.2018

From position 07 to position 18 reduced to 0 MW

D2>DE:

On 02.05.2018

From position 09 to position 18 reduced to 0 MW

On 03.05.2018

From position 07 to position 18 reduced to 0 MW

On 04.05.2018

From position 07 to position 18 reduced to 0 MW

On 05.05.2018

From position 07 to position 18 reduced to 0 MW

Best Regards,

Operations Team