Capacity Curtailment from Germany to Denmark-2 and Denmark-2 to Germany from delivery date 25/08/2017 to 15/09/2017
Dear Market Participants,
The long-term allocated capacity for delivery date 25/08/2017 on the corridor from Germany to Denmark-2 and Denmark-2 to Germany has been curtailed due to Force Majeure.
DE>DK2:
From position 19 to position 24 reduced to 0 MW.
DK2>DE:
From position 19 to position 24 reduced to 0 MW.
The long-term allocated capacity from delivery date 26/08/2017 to 15/09/2017 (inclusive) on the corridor from Germany to Denmark-2 and Denmark-2 to Germany has been curtailed to ensure operation remains within Operational Security Limits.
DE>DK2:
From position 01 to position 24 reduced to 0 MW.
DK2>DE:
From position 01 to position 24 reduced to 0 MW.
Best Regards,