Capacity Curtailment from Germany to Netherlands for delivery date 11/10/2017
Dear Market Participants,
The long-term allocated capacity for delivery date 11/10/2017 on the corridor from Germany to the Netherlands has been curtailed to ensure operation remains within Operational Security Limits.
DE>NL:
On position 1 reduced to 615 MW
On position 2 reduced to 756 MW
On position 5 reduced to 868 MW
On position 6 reduced to 997 MW
On position 7 reduced to 645 MW
On position 8 reduced to 747 MW
On position 9 reduced to 1049 MW
On position 10 reduced to 1025 MW
On position 11 reduced to 971 MW
On position 12 reduced to 949 MW
On position 13 reduced to 615 MW
On position 14 reduced to 723 MW
On position 15 reduced to 734 MW
On position 16 reduced to 866 MW
On position 21 reduced to 1004 MW
Please be aware that the consequences of this reduction might only be visible in the final FB parameters publication around 09:50. Version 2 of the Programming authorizations should be used.
Best Regards,
Operations Team