Capacity Curtailment on the GR-BG border for delivery period 30-07-2025

Published:

1. TSO(s)*:

IPTO (ADMIE)  &  ESO 

2. Identification of affected Long Term Transmission Rights:

GR-BG

3. Triggering event:

Curtailment to ensure operation remains within Operational Security Limits

4. Affected volume in MW / hour for each concerned period:

30-07-2025 00:00 - 01:00 592 MW

30-07-2025 01:00 - 02:00 592 MW

30-07-2025 02:00 - 03:00 592 MW

30-07-2025 03:00 - 04:00 592 MW

30-07-2025 04:00 - 05:00 592 MW

30-07-2025 05:00 - 06:00 592 MW

30-07-2025 06:00 - 07:00 592 MW

30-07-2025 07:00 - 08:00 592 MW

30-07-2025 08:00 - 09:00 592 MW

30-07-2025 09:00 - 10:00 592 MW

30-07-2025 10:00 - 11:00 592 MW

30-07-2025 11:00 - 12:00 592 MW

30-07-2025 12:00 - 13:00 592 MW

30-07-2025 13:00 - 14:00 592 MW

30-07-2025 14:00 - 15:00 592 MW

30-07-2025 15:00 - 16:00 592 MW

30-07-2025 16:00 - 17:00 592 MW

30-07-2025 17:00 - 18:00 592 MW

30-07-2025 18:00 - 19:00 592 MW

30-07-2025 19:00 - 20:00 592 MW

30-07-2025 20:00 - 21:00 592 MW

30-07-2025 21:00 - 22:00 592 MW

30-07-2025 22:00 - 23:00 592 MW

30-07-2025 23:00 - 24:00 592 MW

5. Amount of LTTR remaining after curtailment:

30-07-2025 00:00 - 01:00 469 MW

30-07-2025 01:00 - 02:00 469 MW

30-07-2025 02:00 - 03:00 469 MW

30-07-2025 03:00 - 04:00 469 MW

30-07-2025 04:00 - 05:00 469 MW

30-07-2025 05:00 - 06:00 469 MW

30-07-2025 06:00 - 07:00 469 MW

30-07-2025 07:00 - 08:00 469 MW

30-07-2025 08:00 - 09:00 469 MW

30-07-2025 09:00 - 10:00 469 MW

30-07-2025 10:00 - 11:00 469 MW

30-07-2025 11:00 - 12:00 469 MW

30-07-2025 12:00 - 13:00 469 MW

30-07-2025 13:00 - 14:00 469 MW

30-07-2025 14:00 - 15:00 469 MW

30-07-2025 15:00 - 16:00 469 MW

30-07-2025 16:00 - 17:00 469 MW

30-07-2025 17:00 - 18:00 469 MW

30-07-2025 18:00 - 19:00 469 MW

30-07-2025 19:00 - 20:00 469 MW

30-07-2025 20:00 - 21:00 469 MW

30-07-2025 21:00 - 22:00 469 MW

30-07-2025 22:00 - 23:00 469 MW

30-07-2025 23:00 - 24:00 469 MW

6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment:

For operational security reasons 

7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)?

During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC in the calculation.

*According to section 57.3 of the EU HAR, this field can be filled in within 24 hours after the initial publication