Capacity Curtailment on the GR-IT border for delivery day 10/10/2022
1. TSO(s) *: Terna, Admie
2. Identification of affected Long Term Transmission Rights
Greece to Italy
3. Triggering event:
☒Curtailment to ensure operation remains within Operational Security Limits
☐Curtailment due to Force Majeure
☐Curtailment due to emergency situation
4. Affected volume in MW / hour for each concerned period:
Greece to Italy
10/10/2022
09:00 – 10:00 500 MW
10:00 – 11:00 500 MW
11:00 – 12:00 500 MW
12:00 – 13:00 500 MW
5. Amount of LTTR remaining after curtailment:
Greece to Italy
10/10/2022
09:00 – 10:00 0 MW
10:00 – 11:00 0 MW
11:00 – 12:00 0 MW
12:00 – 13:00 0 MW
6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment *:
HVDC cable ARACTHOS – GALATINA
7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s) *?
Not Applicable