Capacity Curtailment on the HU-AT border for delivery period 05-10-2024
1. TSO(s)*:
APG
2. Identification of affected Long Term Transmission Rights:
HU-AT
3. Triggering event:
Curtailment to ensure operation remains within Operational Security Limits
4. Affected volume in MW / hour for each concerned period:
05-10-2024 00:00 - 01:00 348 MW
05-10-2024 11:00 - 12:00 348 MW
05-10-2024 12:00 - 13:00 348 MW
05-10-2024 13:00 - 14:00 348 MW
05-10-2024 14:00 - 15:00 348 MW
05-10-2024 15:00 - 16:00 348 MW
05-10-2024 16:00 - 17:00 348 MW
05-10-2024 21:00 - 22:00 348 MW
05-10-2024 22:00 - 23:00 348 MW
5. Amount of LTTR remaining after curtailment:
05-10-2024 00:00 - 01:00 313 MW
05-10-2024 11:00 - 12:00 290 MW
05-10-2024 12:00 - 13:00 281 MW
05-10-2024 13:00 - 14:00 286 MW
05-10-2024 14:00 - 15:00 273 MW
05-10-2024 15:00 - 16:00 258 MW
05-10-2024 16:00 - 17:00 294 MW
05-10-2024 21:00 - 22:00 324 MW
05-10-2024 22:00 - 23:00 313 MW
6. Information on exact operational security limit(s) that are expected to be violated in the absence of curtailment*:
Expected violation of operational security limits of physical transmission assets.
7. Why alternative measures are not sufficient to avoid the expected violation of operational security limit(s)*?
During the CC process, all the remedial actions provided by the TSOs are already considered by the CCC in the calculation.
*According to section 57.3 of the EU HAR, this field can be filled in within 24 hours after the initial publication